1-piece MOQ — no tooling fee Any shape · any artwork Dropship worldwide Full JIT management FBA · TEMU · TikTok Shop approved 12 product lines · one factory 1-piece MOQ — no tooling fee Any shape · any artwork Dropship worldwide Full JIT management FBA · TEMU · TikTok Shop approved 12 product lines · one factory
Home/Journal/Spec/Lead times

Journal / Spec & production

Mat Lead Times: 24h Mockup, 3-Day Sample, 15-Day Production

Mat lead times are not a single number — "7–15 days" is a range. The useful version breaks it into steps you can plan around and names the four things that quietly eat another week.

Category: SpecPublished September 20265 min read
Plate 01Floral printed car trunk mat in a black car boot
From machine to pallet

The calendar, step by step

StageTimePrerequisite
Mockup & quoteWithin 24hArtwork plus one measurement, or a photo with a tape measure
Sampling2–3 daysArtwork signed off; sample made on the production line
Printing & cutting2–4 daysFiles finalised, fabric batch allocated
Edge finishing1–2 daysBound, overlocked or hot-cut edge
Packing1–2 daysPackaging in stock or already printed
QC & carton packing1 dayAQL inspection, shipping marks
Sea freight25–35 daysPort to port, plus customs clearance
Air freight5–8 daysDoor to door, charged by chargeable weight

What actually eats the extra week

Artwork not signed off. The single biggest cause of delay is changing files after printing starts. Changing a colour means a reprint; changing a size means a recut.

Nobody checked the measurements. A mat cut to an estimated size arrives and does not fit; rework is a full second pass through the process. Ten minutes with a tape measure is the cheapest insurance in the whole workflow.

Chinese New Year. The country shuts down for two to four weeks around late January or February, with a slow ramp before and after. If your new product launches in Q1, the order must be placed in November.

Fabric or board needs sourcing. Standard base materials are in stock; unusual colours, special backings or 12 mm board may not be, adding 5–10 days before printing can start.

Plate 02Patchwork printed trunk mat trimmed to a station wagon boot floor
Trimmed and packed

Working backwards from your launch date

Say you launch on the 1st and count back: 30 days by sea means cartons leave no later than the 1st of the previous month; 12 days in production means files are finalised by the 20th of the month before that; 3 days for sampling means artwork is signed off a week earlier.

Allow ten weeks of runway for sea freight and four for air. Most first orders go by air to test the market, then switch to sea for reorders — which is why margin only appears from the second order.

What we will not promise

We will not promise a date that depends on files we have not received. If artwork arrives on the 12th, the production clock starts on the 12th — not on the day you asked for a quote.

The one-line versionMockup 24 hours · Sampling 3 days · Production 7–15 days · Air 5–8 days · Sea 25–35 days. Add a week for anything unusual, two weeks if Chinese New Year falls in the window.
Plate 04Geometric printed desk mat with a notebook and pen
Sampling stage

Gallery

On the machine floor

Plate 03
Floral printed car trunk mat in a black car boot
Bulk run01
Patchwork printed trunk mat trimmed to a station wagon boot floor
Cutting02
Geometric printed desk mat with a notebook and pen
Sample03

Frequently asked questions

How fast can a rush order ship?
For a simple mat in a standard size, with artwork finalised and base material in stock, 5–7 days is possible. Die-cut shapes, oversized mats or special backings need the normal 7–15 days. We tell you honestly at the quote stage, not after you have promised a date to your customers.
Does sampling count toward production time?
No — sampling happens before the production schedule. But the 2–3 days it takes are real calendar days, so a first order always includes them. Reorders do not.
How long does shipping to the US take?
Air freight door-to-door is 5–8 days; sea freight port-to-port is 25–35 days, plus customs clearance. Air is charged by chargeable weight, and mats are usually billed by volume rather than weight.
When is capacity tightest?
August to October (ahead of Q4) and the weeks before Chinese New Year. Lock your production slot early in those windows — holding a slot is easy, recovering a missed date is not.
Can you ship directly to Amazon FBA?
Yes — we apply FNSKU labels and carton marks to your shipment's requirements. Fulfilment models →
Can production start before the deposit arrives?
No — but we can hold your slot for about five days before the deposit lands, and artwork prep can run in parallel. What cannot run in parallel is printing itself — that is the step the deposit unlocks.